Construction Update




Construction Update

Construction History

On June 19, 2002 the residents of our district approved a bond referendum for capital improvements to our facilities. For the past year we have been working diligently to complete the projects approved by the residents. In addition, the annual school district budget allocates funds for capital and maintenance projects. The results of our hard work on these projects is clearly visible throughout the district.

The number of projects, the time in which they were completed, and the quality of the work is a testament to the dedicated staff who planned, oversaw and executed the construction work. Where possible, work was scheduled during the school year. Safety was always a primary concern. In these instances the principal, staff and PTAs were involved to ensure that instruction was not disrupted and that all safety and security concerns were addressed. The scope of the combined projects, bond, facilities and maintenance is very impressive. The scope of the projects scheduled for this past summer was an enormous undertaking. But as students and staff returned to school in September there was much excitement as they eyed new bathrooms, counters, windows, art and home and careers classrooms. Each school in the district, even the Administration Building, was part of the renovation.

We are very proud of the results of the work to date. Below you will find a listing of the improvements at each school, along with several photographs. The extensive, but not all inclusive list, includes new boilers, bathrooms, elevators, windows, heating and ventilation, ceilings and lighting, electrical upgrades, computer wiring, new public address systems and fire alarms, roofs, water fountains and water cooler and asphalt and paving throughout the district. Work on various projects is continuing throughout the district. We encourage you to view our power point presentation included on our website that contains many photographs of the work in progress and upon completion. Bond updates are provided at each public monthly Facilities Committee meeting of the Board of Education.

To download a full powerpoint presentation on the improvements made to our facilities click here

If you don't have Powerpoint installed on your computer, click here to download a free Powerpoint Viewer. It must be installed before viewing the presentation.


Burns Avenue

Bond

Boiler Replacement
Roof Coping
Window Replacement
Asphalt Pavement
Concrete Walks & Curbs
Replace Electrical Distribution Panels
Reconstruct Bathrooms
New Telephone System
New PA / Intercom System
Install a Computerized Boiler Control System
Install New Air Compressors
Rehabilitate the Pneumatic Control System & Restore Outside Ventilation
Replace Dampers on Heat & Ventilator Units as needed
Install Backflow Prevention Devices in Boiler Room
Install New Temperature Regulators for Domestic Hot Water System
Replace Lavatory & Classroom Sink Faucets
Replace Existing Water Fountains
Install New Univents at Wing Serviced by June Aire Unit
Recondition Existing Univents
Install New Fire Alarm System that Complies with all ADA Codes
Install New Window Sills & Window Bookcase & Classroom Sink Countertops
Replace Various Acoustical Ceilings with New Suspended Ceiling & Lighting

Capital

Various Minor Masonry Repairs

Maintenance

Resurface Playground with FIBAR
Remove Old Equipment from Playground
Repair Outside Shed
Replace Gym Padding at Stage
Replace Flooring in Various Rooms
Paint Various Rooms & Hallways

Dutch Lane

Bond

Boiler Replacement
Roof & Roof Drain Replacement
Replace Coping & Gravel Stops
Window Replacement
Asphalt Pavement
Concrete walks & Curbs
Replace all Electrical Distribution Panels
Reconstruct Bathrooms
New Telephone System
Install a Computerized Boiler Control System
Install New Air Compressors
Rehabilitate the Pneumatic Control System & Restore Outside Ventilation
Replace Dampers on Heat & Ventilator Units as needed
Install Backflow Prevention Devices in Boiler Room
Install New Temperature Regulators for Domestic Hot Water System
Replace Lavatory & Classroom Sink Faucets
Replace Existing Water Fountains
Install New Univents at Wing Serviced by June Aire Unit
Recondition Existing Univents
Install New Fire Alarm System that Complies with all ADA Codes
Install New Window Sills & Window Bookcase & Classroom Sink Countertops
Replace Various Acoustical Ceilings with New Suspended Ceiling & Lighting

Capital

Various Minor Masonry Repairs

Maintenance

Repair Outside Shed
Replace Flooring in Various Rooms
Paint Various Rooms & Hallways

East Street

Bond

Boiler Replacement
Roof & Roof Drain Replacement
Replace Roof Coping & Gravel Stops
Window Replacement
Asphalt Pavement
Concrete Walks & Curbs
Replace all Electrical Distribution Panels
Install New Handicapped Elevator
Reconstruct Bathrooms
New Telephone System
New PA / Intercom System
Install a Computerized Boiler Control System
Install New Air Compressors
Rehabilitate the Pneumatic Control System & Restore Outside Ventilation
Install three Zone Valves
Install Backflow Prevention Devices in Boiler Room
Install Temperature Regulators for Domestic Hot Water
Replace Lavatory and Classroom Sink Faucets
Replace Existing Water Fountains
Recondition Existing Univents
Install New Fire Alarm System that Complies with all ADA Codes
Install New Window Sills & Window Bookcase & Classroom Sink Countertops
Replace Various Acoustical Ceilings with New Suspended Ceiling & Lighting

Capital

Various Minor Masonry Repairs
Restoration of Terra Cotta Decorative Work

Maintenance

Replace Cafeteria Doors
Replace Flooring in Various Rooms
Paint Various Rooms & Hallways

Fork Lane

Bond

Boiler Replacement
Replace all Gravel Stops
Window Replacement
Asphalt Pavement
Concrete Walks & Curbs
Replace all Electrical Distribution Panels
Reconstruct Bathrooms
New Telephone System
New PA / Intercom System
Install Computer Controlled Boiler System
Install New Air Compressors
Rehabilitate the Pneumatic Control System & Restore Outside Ventilation
Replace Dampers on Heat & Ventilator Units as needed
Install Backflow Prevention Devices in Boiler Room
Install New Temperature Regulators for Domestic Hot Water System
Replace Lavatory & Classroom Sink Faucets
Replace Existing Water Fountains
Recondition Existing Univents
Install New Univents at Wing Serviced by June Aire Unit
Install New Fire Alarm System that Complies with all ADA Codes
Install New Window Sills & Window Bookcase & Classroom Sink Countertops
Replace Various Acoustical Ceilings with New Suspended Ceiling & Lighting

Capital

Various Minor Masonry Repairs

Maintenance

New Entrance Matting
Resurface Kindergarten Playground with FIBAR
Install Panel Truck in Kindergarten Playground
Improve Drainage Outside Faculty Room
Replace Flooring in Various Rooms
Paint Various Rooms & Hallways

Lee Avenue

Bond

Boiler Replacement
Replace all Coping & Gravel Stops
Window Replacement
Asphalt Pavement
Concrete Walks & Curbs
Replace all Electrical Distribution Panels
Install New Handicapped Elevator
Reconstruct Bathrooms
New Telephone System
New PA / Intercom System
Install Computer Controlled Boiler System
Install New Air Compressors
Rehabilitate the Pneumatic Control System & Restore Outside Ventilation
Replace Dampers on Heat & Ventilators as needed
Install Backflow Prevention Devices in Boiler Room
Install Temperature Control Devices for Domestic Hot Water
Replace Existing Water Fountains
Reconstruct Existing Univents
Install New Fire Alarm System that Complies with all ADA Codes
Install New Window Sills & Window Bookcase & Classroom Sink Countertops
Replace Various Acoustical Ceilings with New Suspended Ceiling & Lighting

Capital

Various Minor Masonry Repairs

Maintenance

Renovate Outside Shed
Replace Flooring in Various Rooms
Paint Various Rooms & Hallways

Old Country Road

Bond

Boiler Replacement
Roof & Roof Drain Replacement
Replace all Coping & Gravel Stops
Window Replacement
Asphalt Paving
Concrete Walks & Curbs
Replace All Electrical Distribution Panels
Reconstruct Bathrooms
New Telephone System
New PA / Intercom System
Install Computerized Boiler Controls
Install New Air Compressors
Rehabilitate the Pneumatic Control System & Restore Outside Ventilation
Install Backflow Prevention Devices in Boiler Room
Install New Temperature Regulators for Domestic Hot Water System
Replace Lavatory & Classroom Sink Faucets
Replace Existing Water Fountains
Reconstruct Existing Univents
Install New Univents at Wing Serviced by June Aire Unit
Install New Fire Alarm System that Complies with all ADA Codes
Install New Window Sills & Window Bookcase & Classroom Sink Countertops
Replace Various Acoustical Ceilings with New Suspended Ceiling & Lighting

Capital

Resurface Basketball Court and Replace Partial Fence
Various Minor Masonry Repairs

Maintenance

Resurface Playground with FIBAR
Repair & Paint Concrete Overhang at North Exit Doors
Replace Flooring in Various Rooms
Paint Various Rooms & Hallways

Willet Avenue

Bond

Boiler Replacement
Coping, Fascia & Gravel Stop Replacement
Window Replacement
Asphalt Pavement
Concrete Walks & Curbs
Replace all Electrical Distribution Panels
Reconstruct Bathrooms
New PA / Intercom System
Install a Computerized Boiler Control System
Install New Air Compressors
Rehabilitate the Pneumatic Control System & Restore Outside Ventilation
Install Backflow Prevention Devices in Boiler Room
Replace Lavatory & Classroom Sink Faucets
Replace Existing Water Fountains
Reconstruct Existing Univents
Install New Fire Alarm System that Complies with all ADA Codes
Install New Window Sills & Window Bookcase & Classroom Sink Countertops

Capital

Various Minor Masonry Repairs

Maintenance

None

Woodland

Bond

Boiler Replacement
Roof & Roof Drain Replacement
Replace all Gravel Stops
Asphalt Pavement
Window Replacement
Concrete Walks & Curbs
Replace all Electrical Distribution Panels
Install New Handicapped Elevator
Reconstruct Bathrooms
New Telephone System
Install Computerized Boiler Controls
Install New Air Compressors
Rehabilitate the Pneumatic Control System & Restore Outside Ventilation
Install Backflow Prevention Devices in Boiler Room
Install Temperature Regulators for Domestic Hot Water
Replace Lavatory & Classroom Sink Faucets
Replace Existing Water Fountains
Reconstruct Existing Univents
Install New Fire Alarm System that Complies with all ADA Codes
Install New Window Sills & Window Bookcase & Classroom Sink Countertops
Replace Various Acoustical Ceilings with New Suspended Ceiling & Lighting
Woodland Constuction Project Information Guide

Capital

Various Minor Masonry Repairs
Replace Exterior Phys. Ed Office Door with Masonry

Maintenance

Resurface Kindergarten Playground with FIBAR
Replace Flooring in Various Rooms
Paint Various Rooms & Hallways

Hicksville Middle School

Bond

Boiler Replacement
Roof & Roof Drain Replacement
Replace all Roof Gravel Stops
Asphalt Pavement
Concrete Walks & Curbs
Replace all Electrical Distribution Panels
Reconstruct Bathrooms
Elevator Upgrade to ADA standards
Cupola, Roof Gutters, Moldings & Column Reconstruction
Install Computer Cabling
Provide Computer, Printer, and Large TV Monitor on Bracket for Classrooms
Electrical Service Upgrades
New Telephone System
Install New Air Compressors
Install Zone Valves in the Boiler Room
Rehabilitate the Pneumatic Control System & Restore Outside Ventilation
Install Backflow Prevention Devices in Boiler Room
Replace Existing Water Fountains
Reconstruct Existing Univents
Install New Fire Alarm System that Complies with all ADA Codes
Replace Various Acoustical Ceilings with New Suspended Ceiling & Lighting

Capital

Various Minor Masonry Repairs

Maintenance

Install Outdoor Sign at Front of Building
Paint & Repair Lockers
Renovate Lobby Entrance
Replace Flooring in Various Rooms
Paint Various Rooms & Hallways

Hicksville High School

Bond

Boiler Replacement
Roof & Roof Drain Replacement
Replace all Roof Gravel Stops
Window Replacement
Asphalt Pavement
Concret6e Walks & Curbs
Replace all Electrical Distribution Panels
Reconstruct Bathrooms
Elevator Upgrade
Install Computer Cabling
Provide Computer, Printer, and Large TV Monitor on Bracket for Classrooms
Electrical Service Upgrades
New Telephone System
New PA / Intercom System
Install Zone Valves in the Boiler Room
Rehabilitate the Pneumatic Control System & Restore Outside Ventilation
Install Backflow Prevention Devices in Boiler Room
Replace Existing Water Fountains
Reconstruct Existing Univents
Install New Fire Alarm System that Complies with all ADA Codes
Replace Various Acoustical Ceilings with New Suspended Ceiling & Lighting

Capital

Renovate Auditorium Stage & House Lighting
Replace 14 Smoke Doors
Replace Fencing at Tennis Courts
Renovate Little Theater
Various Minor Masonry Repairs

Maintenance

Remove Asphalt Courtyard Seating Area
Renovate Vestibule at Room 118
Renovate Handball Court Playing Surface
Replace Art Wing Exterior Doors
Sand Blast and Paint Stadium Bleacher Superstructure
Renovate Home Economics Room
Replace Main Staircase Stair Treads
Paint & Repair Lockers
Replace Flooring in Various Rooms
Paint Various Rooms & Hallways

Administration Building

Bond

Window Replacement
Boiler Replacement
Renovate Bathrooms for Handicapped Accessibility
New Telephone System
Install New Fire Alarm System that Complies with all ADA Codes

Capital

None

Maintenance

Create Bathroom for Computer Training & CSE Conference Rooms
Install Video Component of Board Room A/V System